Sheet02 / 08
Redline · pre-load checkThe check
Rev A2026-10-22
StatusBRC-28BLOCK

The check, Trace

Trace

One record followed through every rule.

Trace, milestone · BRC-28

BRC-MS06 S.O.P.

Fields as mapped Sample data

idBRC-MS06
programCodeBRC-28
nameS.O.P.
date2028-07-08
baselineDate2028-06-14
isGatetrue
gateCodeG5
ownerProgram manager
wbsIdBRC-W00

Legacy row: ms_id=BRC-MS06 prog_cd=BRC-28 ms_nm=S.O.P. ms_dt=08/07/2028 bl_dt=14/06/2028 gate_flg=Y gate_cd=G5 owner=Program manager wbs=BRC-W00

Every rule on this record

  1. R1Gate sequence integrityNo finding
  2. R2Dependency logicNo finding
  3. R3Working calendarREVIEW
  4. R4Key reconciliationNo finding
  5. R5Naming variantsREVIEW
  6. R6Over-allocationNo finding
  7. R7Baseline driftREVIEW
  8. R8Financial rollupNo finding
  9. R9OrphansNo finding
  10. R10Required fields for loadNo finding
R3-03REVIEWOpen

S.O.P. lands on 2028-07-08, Saturday.

Proposed fix. Shift to 2028-07-10, the next working day (sample policy: forward).

date
2028-07-08
weekday
Saturday
holiday
(empty)
proposed
2028-07-10
R5-02REVIEWOpen

"S.O.P." is a variant of "Start of production".

Proposed fix. Rename to "Start of production".

value
S.O.P.
canonical
Start of production
R7-02REVIEWOpen

S.O.P. sits 24 days after its baseline 2028-06-14, with no change record.

Proposed fix. Attach the approved change record, or return the date to baseline.

date
2028-07-08
baseline
2028-06-14
driftDays
24

Sheet index

  1. 01CoverWho built Redline, what the check does, and where to start.
  2. 02The checkThe working tool: programs, rules, trace, ledger, gate, SQL bench, drift.2 of 3 blockedBLOCK
  3. 03Case studyContext, observations, solution, measurement plan, and limits.
  4. 04Readiness auditPrioritized findings with evidence, printable.
  5. 05WorkbookSix guided exercises on the sample data.
  6. 06First 90 daysSix two-week sprints with stories and acceptance criteria.
  7. 07FitRequirement to evidence map, with the gaps stated plainly.
  8. 08SystemTokens, components, motion spec, and how to adapt the set.
  9. ATTAttachmentsResume, cover letter, sample data, and session exports.

Arrow keys move. Enter opens. Esc closes.