The check, Drift
Drift
Legacy against loaded, for the parallel run.
During a parallel run the legacy tool stays live while Planisware takes over. Run this diff every week: legacy export against post-load export. A date which moved in one system and not the other shows up here before the steering meeting does.
Scope
- Snapshots
- 2026-10-01 against 2026-10-15
- Dates changed
- 5
- Max shift
- 12 days
- Activities missing
- 2
- Resources renamed
- 2
| Milestone | Program | Legacy planning tool export | Post-load export | Shift, days |
|---|---|---|---|---|
| ALD-MS13 Homologation granted | ALD-27 | 2028-06-26 | 2028-06-29 | +3 |
| BRC-MS09 Prototype release | BRC-28 | 2027-06-15 | 2027-06-13 | -2 |
| BRC-MS11 First part shipped | BRC-28 | 2028-01-07 | 2028-01-19 | +12 |
| CDR-MS12 Part approval granted | CDR-27 | 2028-05-26 | 2028-05-31 | +5 |
| CDR-MS14 Launch review | CDR-27 | 2028-08-28 | 2028-09-04 | +7 |
| Activity | Program |
|---|---|
| BRC-A41 Ramp-up monitoring | BRC-28 |
| CDR-A47 Program closeout report | CDR-27 |
| Code | Legacy name | Loaded name |
|---|---|---|
| RES-009 | Electrical integration engineer 4 | Electrical integration engineer 4 (contract) |
| RES-021 | Program controls analyst 2 | Program controls analyst 2 (Cost) |