Sheet02 / 08
Redline · pre-load checkThe check
Rev A2026-10-22
StatusBRC-28BLOCK

The check, Ledger

Ledger

Every finding, with status and notes.

Scope
Severity
Rule
11 findings, as of page load, sorted by severity then ruleSample data
Finding idRuleSeverityProgramRecordMessageProposed fixStatusNote
R1BLOCKBRC-28program:BRC-28:G4Program Birch has no G4 Pre-production build milestone.Add G4 from the gate template and confirm the date with the program owner.OpenNone
R2BLOCKBRC-28dependency:BRC-D005BRC-A07 starts 2027-03-12, before BRC-A06 finishes 2027-03-18 plus 2 days lag.Move BRC-A07 start to 2027-03-20 or later, or confirm the link type with the planner.OpenNone
R2BLOCKBRC-28dependency:BRC-D012BRC-A12 starts 2027-07-12, before BRC-A11 finishes 2027-07-16 plus 3 days lag.Move BRC-A12 start to 2027-07-19 or later, or confirm the link type with the planner.OpenNone
R4BLOCKBRC-28assignment:BRC-AS007Assignment BRC-AS007 uses resource code RES-0O7, which is not in the resource master.Proposal: RES-007 (1 character edit). Confirm with resource planning before changing.OpenNone
R8BLOCKBRC-28wbs:BRC-W20BRC-W20 budget 1,990,000 differs from its children total 2,015,000 by -25,000.Correct the child budget with finance, or restate the parent. The loader takes the rollup as entered.OpenNone
R9BLOCKBRC-28activity:BRC-A30BRC-A30 Software release 2 points to WBS BRC-W99, which does not exist.Reassign the activity to an existing WBS node with the program controls lead.OpenNone
R10BLOCKBRC-28milestone:BRC-MS10milestone BRC-MS10 has no owner (legacy column owner).Fill owner in the source export, or ask the owner for the value. The loader requires the field.OpenNone
R3REVIEWBRC-28milestone:BRC-MS06S.O.P. lands on 2028-07-08, Saturday.Shift to 2028-07-10, the next working day (sample policy: forward).OpenNone
R5REVIEWBRC-28milestone:BRC-MS06"S.O.P." is a variant of "Start of production".Rename to "Start of production".OpenNone
R6REVIEWBRC-28resource:RES-004@2027-09RES-004 carries 203 h against 150 h capacity in 2027-09 (135 percent).Move 53 h to another 2027-09 resource or period with resource planning.OpenNone
R7REVIEWBRC-28milestone:BRC-MS06S.O.P. sits 24 days after its baseline 2028-06-14, with no change record.Attach the approved change record, or return the date to baseline.OpenNone

Sheet index

  1. 01CoverWho built Redline, what the check does, and where to start.
  2. 02The checkThe working tool: programs, rules, trace, ledger, gate, SQL bench, drift.2 of 3 blockedBLOCK
  3. 03Case studyContext, observations, solution, measurement plan, and limits.
  4. 04Readiness auditPrioritized findings with evidence, printable.
  5. 05WorkbookSix guided exercises on the sample data.
  6. 06First 90 daysSix two-week sprints with stories and acceptance criteria.
  7. 07FitRequirement to evidence map, with the gaps stated plainly.
  8. 08SystemTokens, components, motion spec, and how to adapt the set.
  9. ATTAttachmentsResume, cover letter, sample data, and session exports.

Arrow keys move. Enter opens. Esc closes.